Technical Assistance in preparing the Power Transmission Enhancement Project |
In 2008 Corporate Solutions was awarded a contract under the ADB’s small-scale technical assistance to assist the Government of Azerbaijan in preparing the Power Transmission Enhancement Project suitable for ADB financing. The assignment involves financial and economic analysis of the investment projectwhich will construct a double circuit 220 kV transmission line with a total length of 280 km between the “Mingechaur” hydropower plant and the 500/330/220 kV “Absheron” substation. The new 220 kV transmission line will run along a pre-determined route through the rugged foothill of the country. |